Cable sizing is the most fundamental calculation in LV electrical design. Pick a cable that is too small and it overheats — becoming a fire hazard and a reliability risk. Pick one that is too large and you waste material and cost. IS 732 (Code of Practice for Electrical Wiring Installations) mandates that every cable satisfies two simultaneous criteria: current carrying capacity and voltage drop. Both checks must pass — whichever requires the larger cable governs.
The Two-Criteria Rule of IS 732
Criterion 1 — Current Carrying Capacity (Thermal Limit)
Every cable has a maximum continuous current rating determined by its conductor cross-section, insulation type, and installation method. Exceeding this rating causes the insulation to overheat, degrade, and potentially cause fire. IS 732 Tables 4–9 give rated currents for various cable sizes and installation methods at a base ambient temperature of 30°C.
Criterion 2 — Voltage Drop (3% Limit)
Even if a cable can thermally carry the current, a thin long cable in a long run may cause excessive voltage drop. IS 732 limits this to 3% of the nominal supply voltage on any branch circuit. For 230V single-phase: max 6.9V. For 415V three-phase: max 12.45V.
Step-by-Step Cable Sizing Method
Step 1 — Calculate Design Current
Step 2 — Select Cable from IS 732 Tables (Thermal Check)
Select a cable whose derated current capacity ≥ design current. Derate the tabulated current for installation method and ambient temperature:
Step 3 — Apply Derating Factors
Installation Method Factor: IS 732 base tables assume cables clipped direct to surface. For other methods:
| Installation Method | Factor vs Clipped Direct |
|---|---|
| Clipped direct (base) | 1.00 |
| In conduit (single cable) | 0.90 |
| In trunking (touching) | 0.80 |
| Buried in ground (direct) | 0.85–1.00 (soil dependent) |
Grouping Factor (Cg) — IS 732 Table 22:
| No. of Cables Grouped | Cg (touching, enclosed) |
|---|---|
| 1 | 1.00 |
| 2 | 0.80 |
| 3 | 0.70 |
| 4 | 0.65 |
| 6 | 0.57 |
| 9 | 0.50 |
Ambient Temperature Factor (Ca) — IS 732 Table 16 (for 70°C PVC cables):
| Ambient Temp (°C) | Ca |
|---|---|
| 25 | 1.03 |
| 30 (base) | 1.00 |
| 35 | 0.94 |
| 40 | 0.87 |
| 45 | 0.79 |
| 50 | 0.71 |
Step 4 — Check Voltage Drop
Fully Worked Example
Problem: Size a cable for a 7.5 kW, 415V three-phase motor located 65m from the MCC. The cable runs in a conduit with 2 other circuits (3 circuits total). Ambient temperature is 40°C. Cable type: Copper PVC (4-core).
Use our Cable Size Calculator to check both IS 732 criteria simultaneously for any single-phase or three-phase circuit. Also use the Voltage Drop Calculator to quickly verify drop on any proposed cable size.
IS 732 Cable Current Capacity — Quick Reference (Copper PVC, Clipped Direct, 30°C)
| Cable Size (mm²) | Single Phase (A) | Three Phase (A) |
|---|---|---|
| 1.5 | 17.5 | 15.5 |
| 2.5 | 24 | 21 |
| 4 | 32 | 28 |
| 6 | 41 | 36 |
| 10 | 57 | 50 |
| 16 | 76 | 68 |
| 25 | 101 | 89 |
| 35 | 125 | 110 |
| 50 | 151 | 134 |
Common Cable Sizing Mistakes
- Applying only the thermal check: Many engineers size cables for current capacity alone without checking voltage drop. For runs over 40–50m, voltage drop almost always requires a larger cable.
- Not applying all derating factors simultaneously: Ambient temperature AND grouping factors must both be applied. In a plant room at 45°C with 6 cables in a trunking, the combined derating can be 0.79 × 0.57 = 0.45 — less than half the base rating.
- Using the same cable for both the motor feeder and the control circuit: Control cables (4-core 1.5mm²) must be separate from power cables. Never run control and power in the same conduit per IS 732.
- Ignoring the protective conductor (earth) size: IS 732 Table 54-7 specifies minimum earth conductor size based on the phase conductor size. For 16mm² phase conductor, the minimum earth conductor is 16mm²; for 50mm²+, the earth must be 25mm².
Conclusion
Cable sizing per IS 732 is a two-step process: first confirm thermal adequacy with correct derating, then verify that voltage drop at the design current stays within 3%. Both checks must pass. The larger resulting cable size governs. This systematic approach ensures your electrical installation is safe, code-compliant, and performs reliably throughout its service life.
Use the MEPMate Cable Size Calculator to automate both checks for any LV circuit in seconds.